Construction of section in Aktobe region, project “Western Europe-Western China” is given to Turkish company «Cengiz Insaat Sanayi ve Ticaret» LLP (Тurkey).

As of 11th of July, 2011 Contractor – «Cengiz Insaat Sanayi ve Ticaret» (Turkey) for works on site 835 persons are mobilized, 3 of them – foreign experts, 785 – local and 44 – from other regions of country.

Equipment mobilized – 22 units, 134 units belong to Contractor itself.

Total procurement of crushed stone for asphalt concrete production and installation of foundation – 151,58 thousand m3 with requirement of 346,80 thousand m3 for current 2011.  

In June of this year the Contractor started production of coarse grained high porous asphalt concrete mix, which was placed to bottom layer of crushed stone on one from sections of constructed road sections. According to conclusions of supervision services, material is fully conforms to Specification.

Provision by survey instruments are for 100%. Also Contractor fully provided mobilization of mobile laboratory of construction equipment, stated in bidding documents. However, hasn’t completed the installation of area in laboratory.

In order to improve the administration activity, especially the work of company on planning and control, the mobilization of foreign staff is being continued..

As of today Contractor has number of claims to designer – “Doris” LLP, which should solve number of issues, namely issues on installation of pass over railway, relocation of well, reinstallation of separate communications and gas pipeline on some sections and other issues.